Steel Design
eBook - ePub

Steel Design

Paul McMullin, Jonathan Price, Richard Seelos, Paul W. McMullin, Jonathan S. Price, Richard T. Seelos

Compartir libro
  1. 312 páginas
  2. English
  3. ePUB (apto para móviles)
  4. Disponible en iOS y Android
eBook - ePub

Steel Design

Paul McMullin, Jonathan Price, Richard Seelos, Paul W. McMullin, Jonathan S. Price, Richard T. Seelos

Detalles del libro
Vista previa del libro
Índice
Citas

Información del libro

Steel Design covers steel design fundamentals for architects and engineers, such as tension elements, flexural elements, shear and torsion, compression elements, connections, and lateral design. As part of the Architect's Guidebooks to Structures series it provides a comprehensive overview using both imperial and metric units of measurement. Each chapter includes design steps, rules of thumb, and design examples. This book is meant for both professionals and for students taking structures courses or comprehensive studies. As a compact summary of key ideas, it is ideal for anyone needing a quick guide to steel design. More than 150 black and white images are included.

Preguntas frecuentes

¿Cómo cancelo mi suscripción?
Simplemente, dirígete a la sección ajustes de la cuenta y haz clic en «Cancelar suscripción». Así de sencillo. Después de cancelar tu suscripción, esta permanecerá activa el tiempo restante que hayas pagado. Obtén más información aquí.
¿Cómo descargo los libros?
Por el momento, todos nuestros libros ePub adaptables a dispositivos móviles se pueden descargar a través de la aplicación. La mayor parte de nuestros PDF también se puede descargar y ya estamos trabajando para que el resto también sea descargable. Obtén más información aquí.
¿En qué se diferencian los planes de precios?
Ambos planes te permiten acceder por completo a la biblioteca y a todas las funciones de Perlego. Las únicas diferencias son el precio y el período de suscripción: con el plan anual ahorrarás en torno a un 30 % en comparación con 12 meses de un plan mensual.
¿Qué es Perlego?
Somos un servicio de suscripción de libros de texto en línea que te permite acceder a toda una biblioteca en línea por menos de lo que cuesta un libro al mes. Con más de un millón de libros sobre más de 1000 categorías, ¡tenemos todo lo que necesitas! Obtén más información aquí.
¿Perlego ofrece la función de texto a voz?
Busca el símbolo de lectura en voz alta en tu próximo libro para ver si puedes escucharlo. La herramienta de lectura en voz alta lee el texto en voz alta por ti, resaltando el texto a medida que se lee. Puedes pausarla, acelerarla y ralentizarla. Obtén más información aquí.
¿Es Steel Design un PDF/ePUB en línea?
Sí, puedes acceder a Steel Design de Paul McMullin, Jonathan Price, Richard Seelos, Paul W. McMullin, Jonathan S. Price, Richard T. Seelos en formato PDF o ePUB, así como a otros libros populares de Architecture y Architecture Methods & Materials. Tenemos más de un millón de libros disponibles en nuestro catálogo para que explores.

Información

Editorial
Routledge
Año
2017
ISBN
9781317568155

Chapter 1
LeBow Business Building

Jonathan S. Price
1.1 Introduction
1.2 Design Development
1.3 Construction Documents
1.4 Construction Administration
1.5 Opening
Figure 1.1 LeBow Building
Figure 1.1 LeBow Building
Source: Keast & Hood
The construction of any significant work requires hard work both intellectually and physically. Honesty, adaptability, and attention to detail help also. The LeBow School of Business is a case in point. From its outset, the project was a challenge to the entire team. The only predictable outcome was that a new building would be constructed. Its appearance, size, shape, and final cost would be determined by those who would mold the clay that started as an idea, and finished with an opening that belied the struggle we all went through to see it completed.

1.1 Introduction

Bennett LeBow is a Drexel University Graduate and a Philadelphia native. His generosity provided the major funding necessary to construct the LeBow College of Business. When the project was announced, several well-known architects competed for the commission. The winning team was Robert A. M Stern with Voith-MacTavish Architects.
The proposed site was occupied by Matheson Hall, a depressing, four-story, 60s-style structure facing Market Street. Before Matheson was constructed, row houses and small buildings lined both Woodland Avenue and Market Streets.
Figure 1.2 West Philadelphia c. 1895, showing building site names annotated
Figure 1.2 West Philadelphia c. 1895, showing building site names annotated
Source: Philageohistory.org
Incorporating Matheson Hall was an early goal but its restrictive headroom, shallow basement, narrow bays, and small foundations limited the new design. Reinforcing the structure and living with the existing column grid would negate any savings and compromise the program. Matheson had to go.
About 30 ft (9.1 m) below Market Street is Philadelphia’s main east–west commuter line, the Market–Frankford EL (elevated). This subterranean structure presented challenges but helped in other ways as will be discussed. Other non-yielding site features included public utilities within the Market and Woodland Avenue rights of way. Taken together, these restrictions defined a tight triangular property, shown in Figure 1.2.
Reflecting the site, a triangular plan evolved with symmetry about the long bisector. The two long sides or “bars” define a central, 7-story-high atrium. The shortest bar is the tallest at 12 stories and houses faculty offices and classrooms. The other two bars are about half as high at 7 stories each and support classrooms, large meeting rooms, and a very large, lower level auditorium.

1.2 Design Development

With an aggressive schedule and many unknowns, a steel frame was the logical choice for its inherent strength and design flexibility. Steel costs were disproportionately high and the structural engineers looked for savings. After the initial modeling was complete, the steel weighed-in at approximately 18 psf, including columns. This was too heavy so we explored ways to reduce the weight. Some of this high weight was attributable to wide bays, initial conservatism, and an excessive number of heavy column transfers required by floor plan alignment (or misalignment) between levels.
Value Engineering (VE), often bemoaned by design teams, is a CM-driven process to identify potential savings used to meet a construction budget. On LeBow, VE offered difficult choices. One of the least palatable was to shell some of the tower office levels pending added funding for fit-out (shell means build the space without finishes).
Motivated by the cost pressure, the architects reworked the plans to better align walls (and columns) between floors. Some column transfers were inevitable, such as those above the large subterranean auditorium. We worked on reducing our initial conservatism on the structure.
Other challenges that surfaced were below grade. Based on groundwater observation wells, the geotechnical engineer recommended we design for 8 feet (2.44 m) of hydrostatic pressure beneath the lower level. This impacted the site development costs and drove the design decision to use a mat foundation system acting as a very large boat. A blessing in disguise, the Market Street subway with its own system of drains, helped lower the groundwater by acting as a large French drain during construction.
Our solution for spanning over the lower level auditorium was to design story-high trusses extending from the 2nd to the 3rd floors to be concealed behind the atrium walls (Figure 1.3). Temporary columns supported the first, second, and third floor framing until the trusses were built and stabilized. The columns between levels one and two, below the trusses, were initially in compression but became hangers after the trusses were put into service.
Figure 1.3 Truss TR-2 Elevation
Figure 1.3 Truss TR-2 Elevation
Source: Keast & Hood
The trusses above the auditorium were modeled in STAAD® as simply supported plane trusses with one top chord support pinned and the other on a roller. The bottom chords were modeled with roller or slide supports.
Cantilevers, another device used to convey weightlessness, spawned the question “how thin can you make it?” As the engineers for many architecturally driven projects, we try hard to provide an economical solution but are mindful of the architects’ wishes. This came into play on the eastern façade where we absorbed the structure into the slab, saving 5 in (127 mm) of depth, shown in Figure 1.5. This was at no small cost from an engineering and construction standpoint, but was important architecturally.
At the northwest corner adjacent to Market Street, a cantilevered corner was structured with a large diagonal rod that would remain visible behind the aluminum curtain wall and became a design feature, shown in Figure 1.6. We cantilevered orthogonal W24 × 104 from the nearest point on line N1 to provide needed redundancy and stability during erection until the 2 in (51 mm)-diameter diagonal rod was installed and tensioned.
Figure 1.4 Truss TR-2 Column Connections
Figure 1.4 Truss TR-2 Column Connections
Source: Keast & Hood
Resisting lateral loads presented a larger challenge. Surrounding the elevator and stair core and rising some 250 ft (46 m) above the foundations, the tower had its own diagonally braced core. Because the building was to be relatively long in the east–west direction, the broader 7-story section off to the east demanded a lateral system of its own. For that, we designed concrete shear walls around the easternmost stair rising 7 stories.
The two bracing systems responded very differently. In our model; the steel core bracing acted as a tall-cantilevered truss and the shear walls as squat, rigid elements of the structure. The shear walls attracted tremendous forces from the tower bracing system. Rather than separating the two systems with an expansion joint, as would be required in a high seismic area, we decided to join them with drag struts at the 5th and 6th floors.
Figure 1.5 Slab Extension
Figure 1.5 Slab Extension
Source: Keast & Hood
With the potential of large temperature swings during construction, we were also concerned that thermal forces might overstress the drag struts. If restrained against shrinkage or expansion, steel and concrete can overwhelm connections to supports. Bridge designers know this well and therefore connect one end of bridges on roller supports so the structure can “breathe” with seasonal temperature changes.
Façade elements were another challenge. Panel weights and restrictive deflection limitations forced the spandrel beams to be very heavy. The architectural precast wall panels were designed as 8-foot (2.44 m) wide, 2-story tall elements imposing their weight eccentrically on spandrel beams. We designed rotation counters perpendicular to these spandrel beams but our assumed eccentricity of 6 in (152 mm) to the precast load was not enough. When the shop drawings arrived, we saw they had between 8 and 10 in (203 and 254 mm) of eccentricity and the loads did not align well with the rotational restraint of the beams.
Figure 1.6 N-W Corner Diagonal Brace
Figure 1.6 N-W Corner Diagonal Brace
Source: Keast & Hood
In hindsight, we might have been better off with structural tubes as spandrel beams or plating one side of the wide flange members to add torsional strength and rigidity. The fix was field installation of diagonal kickers at precast connection locations not backed up by a torsional restraint beam.
Another challenge we faced was with the glass curtain wall contractor who wanted to “panelize” his system to expedite erection and decrease labor costs. The architecture did not permit topside connections to the slab so the connections were hidden below. This under-slab connection suggested by the envelope consultant and designed by the curtain wall...