Do recent moves in the construction industry towards collaborative working and other new procurement procedures really make good business sense? Procurement in the Construction Industry is the result of research into this question and it includes the first rigorous categorizing of the differences between procurement methods currently in use. In the process of carrying out this research, the team has produced a comprehensive study of procurement methods which looks in detail at the relative benefits and costs of different ways of working, with sometimes surprising results. As such, it is not only a valuable guide for practitioners on the complexities of the procurement process, but also an outline of the relevance of economic theory to the construction sector.
Frequently asked questions
Information
1 Introduction
The idea for this research project into the costs of procurement in the construction industry was born at a time of great interest throughout the industrialized world in the development of innovative working practices in the management of the commercial processes of the construction industries. The new thinking included new methods of financing projects, such as the development of PFI (PPP); new methods of procurement and new collaborative working practices. These were sometimes introduced as separate innovations but in many cases there was a combination of two or three of the developments in one project or group of projects. One of the changes taking place was the increasing involvement of the client in the movement for change, not only in the public sector, but also by the private client organizations with long term construction programmes. The impetus for change was so great that it seemed that a new era was dawning in the commercial arrangements for contracting, replacing the largely confrontational and adversarial approaches of the past. There had been a considerable amount of discussion on the advantages of the new methods of working, both realized and anticipated, in terms of a better or cheaper product or faster delivery times. However, there was very little consideration on the costs of procurement throughout the whole construction process.
- competitive bidding is not the only criterion upon which contractors, consultants and suppliers are selected,
- some reliance is placed on the deliberate development of long-term working relationships,
- there is a limited number of partners.
2 Review of existing knowledge
There is much research that helps provide a context for work in this area. The research was based on the idea of investigating the cost consequences of the kind of collaborative working practices called for by various strategic reports on the construction industry. In order to deal with these consequences, the distinguishing characteristics of different procurement methods need to be articulated. Further, since there are commercial transactions at every level in the supply chain, work on supply chain mapping sheds light on the scale of transactions in construction projects. There has been much theoretical work, based on the costs of transactions, which seeks to provide explanations for the existence of firms and markets (i.e. the decision about whether to make or buy supplies). While this work provides a useful starting point for defining transaction costs, the focus is not on the choice between firms and markets, but on different ways of selecting and contracting with supply chain partners. There has been some interesting work investigating the factors that affect the costs of procurement, and some work on assessing the costs. This section of the report describes the previous work done in these areas, providing the context for the research carried out.
2.1 CALLS FOR CHANGE
Tendering was among the main issues tackled by the Latham Report, a joint government-industry review of procurement and contractual arrangements, published in the UK in 1994. It would probably be no exaggeration to say that Latham sees traditional tendering as âthe root of adversarial attitudesâ (for example, Latham 1994: 58). In his earlier, interim report, he levelled a number of serious criticisms at the industryâs traditional tendering process. These included the sheer expense of complying with tender procedures (particularly for design and build work), the excessive length of tender lists, and the existence, particularly at the level of sub-contract tendering, of âmalpracticesâ such as âDutch auctioningâ and âbid peddlingâ (Latham 1993: 28). The prevalence of Dutch auctioning and bid peddling are perfect examples of the failure of traditional tendering: carried out with the aim of price-reduction, the effect of both is to undermine the willingness of a prospective contractor to commit to best price in the initial tender (Construction Industry Board 1997a: 21). Lathamâs recommendations on tendering show a particular concern that public sector clients, while being aware of European Union Directives, should tender selectively and adhere to established codes of procedure. Clients who âseek tenders on a design and build basisâ should be particularly aware of the costs of bidding for this type of work, and modify their selection procedures accordingly (Latham 1994: 57). Latham also noted that local authorities were being âseverely hampered by being forced to accept the lowest tenderâ often neglecting other aspects of âvalue for moneyâ (Latham 1994: 58). Four of Lathamâs 30 specific recommendations in the executive summary (Latham 1994: vii-ix) refer to tendering:
- The Construction Industry Council should publish a code of practice dealing with âproject management and tendering issuesâ.
- âTender list arrangements should be rationalized ⌠and advice issued on partneringâ.
- âTenders should be evaluated ⌠on quality as well as priceâ and recommendations on tender periods should be followed.
- âA code of practice for the selection of sub-contractors should be drawn upâ ⌠with âshort tender listsâ and âfair tendering proceduresâ.
- Clear and transparent procedures should be followed.
- Tender lists should be compiled systematically and be as short as possible.
- Conditions should be the same for all tenderers.
- Confidentiality should be respected.
- Sufficient time is to be allowed for tendering.
- Sufficient information should be provided.
- Tenders should be assessed on quality as well as price.
- Tender prices should not change on an unaltered scope of works.
2.2 CHARACTERISTICS OF PROCUREMENT OPTIONS
Within the construction sector, procurement has become a complex and difficult topic. This is because it refers not only to what is bought, but also to a diverse array of methods for acquiring a huge range of buildings and infrastructure facilities. Before developing a general view of how procurement options differ, it is useful to identify the main features of current procurement approaches. There are methods of contracting and/or funding, methods of selection and methods of payment.
2.2.1 Methods of contracting
- General contracting: Design is provided by independent consultants in direct contract with the client or (in the public sector) designers that are part of the client organization. A separate contract for the construction of the project is placed with a building contractor, who then sub-lets elements of the work. Payment for the building work is monthly, based on how much work has been done to date, in relation to a tendered lump sum, based on unit rates in a contractual bill of quantities. Selection is normally by competitive tender, though the tender list is often pre-selected, rather than open.
- Design and build (pure): Design and Build (D&B) is a procurement system where a single organization undertakes the responsibilities and risks for both the design and construction phases. There may be various levels of employer-involvement in the design: in the âpureâ form of D&B, the client engages a building contractor at the outset (after competition or otherwise) who is then responsible both for the design and the construction of the work. The typical payment method for D&B is a lump sum, payable in monthly instalments, based on a cost document that forms part of the âContractorâs Proposalsâ which is itself a tendered or negotiated response to the âEmployerâs Requirementsâ, documents that form the basis of the contract.
- Novated design and build: A widely used variation of D&B occurs when the client employs a design team for the early stages of the project (typically up to the planning permission stage) to prepare the outline design and an âEmployerâs Requirementsâ document. A building contractor is selected by tender or other means and the design team is then transferred to this builder, and it is this transfer of contracts from the client to the builder that is called novation. The design team then continues to prepare a detailed design. The...
Table of contents
- COVER PAGE
- TITLE PAGE
- COPYRIGHT PAGE
- ACKNOWLEDGEMENTS
- EXECUTIVE SUMMARY
- 1. INTRODUCTION
- 2. REVIEW OF EXISTING KNOWLEDGE
- 3. RESEARCH
- 4. FRESH PERSPECTIVES ON CONSTRUCTION PROCUREMENT
- 5. CONCLUSIONS AND RECOMMENDATIONS FOR FURTHER WORK
- 6. REFERENCES
- APPENDIX A: GLOSSARY OF TERMS
- APPENDIX B: ANNOTATED BIBLIOGRAPHY